Planned road and pavement improvements 2018

Pavements

There are currently 4 pavement schemes in progress/due to begin across the borough within this month.

Road Name

Ward

Start Date

Expected Finish

Highfield Avenue

Golders Green

12/02/18

29/06/18

Hutton Grove

West Finchley

05/03/18

08/0618

Holden Road

Totteridge

12/03/18

10/08/18

Green Road

Totteridge

14/05/18

09/07/18

Cherry Tree Road

East Finchley

21/05/18

13/07/18

Longland Drive

Totteridge

29/05/18

26/10/18

Hampstead Heights

East Finchley

29/05/18

17/08/18

Friern Barnet Lane

Coppetts

11/06/18

03/08/18

Trinity Avenue

East Finchley

18/06/18

03/08/18

 